Co-op Power Restoration Efforts Continue Amid Florence’s Flooding Threats
PublishedSeptember 18, 2018
Author
Derrill Holly
Share
Currently Reading
Co-op Power Restoration Efforts Continue Amid Florence’s Flooding Threats
Updated: Sept. 18, 8:45 a.m.
When electric cooperative employees and their consumer-members remember the storm known as Florence, many will likely talk about it as two events that hit back to back, with winds and heavy rain first, followed by flooding that pushed streams and rivers into subdivisions and neighborhoods.
“All the water that came in when Florence was a hurricane or tropical storm is now headed back toward the coast as stormwater runoff,” said Gay Johnson, director of corporate communications at Four County Electric Membership Corp. “We have a lot of flooded roads and debris, including broken limbs and uprooted trees that are blocking the roadways, so we still can’t get to many of the areas we need to reach to repair the lines.”
The Burgaw, North Carolina-based co-op had 17,000 meters out as of Tuesday morning.
“We’re answering calls 24/7, with member service reps working 7 a.m. to 7 p.m., before they are relieved by the night shift that covers phones until morning,” said Johnson. “We’re all staying here, because our headquarters is like an island, with everything flooded around us.”
While flash flooding has been the problem in many areas, the focus is now on river and stream flooding, with dozens of major waterways still days away from cresting. As electric cooperative crews work nonstop to restore power, co-ops are warning their members that more outages could come.
With the Northeast Cape Fear River already out of its banks and inland flooding still getting worse, some co-op-served communities that suffered days of torrential rains and gale-force winds are likely to see waters rise again in the days ahead.
“The rivers have not crested yet, so if we were even able to get home, we might not be able to get back,” said Johnson. “This is a catastrophic event that we could be facing like this for as long as two weeks.”
Power restoration efforts have quickly reduced the numbers of co-op meters out of service as a result of wind damage over the weekend. Outage numbers in co-op-served territories in North Carolina were down to 112,000 on Tuesday morning from a high of 326,000 on Friday.
For Newport, North Carolina-based Carteret-Craven Electric Cooperative, ongoing transmission issues still being repaired by investor-owned utility crews have kept the co-op from restoring service to about two-thirds of its overall membership.
“We’ve been able to power up several substations from our transmission substation,” said the co-op’s communications director, Lisa Galizia. “We’ve done that to get power on where we can, but there are still some places we still can’t reach.”
But across the co-op’s service territory, more than 280 lineworkers and tree crew members have been busy rebuilding the system so that when the substations are re-energized, more subdivisions and neighborhoods will be quickly put back online.
“We’ve got a crew on every circuit coming out of every substation,” said Galizia. “While they’re running into some issues, the water is starting to recede. Conditions are soggy, but they’re working in there to do what they can.”
With parts of many roads closed in North and South Carolina, including some stretches of Interstate 95, crews in many hard-hit areas have faced detours reaching areas where they safely can restore power.
Holston Electric Cooperative sent 9 lineworkers to Lumbee River Electric Membership Corporation in Red Springs, NC to assist with Hurricane Florence recovery efforts. (Photo courtesy: Holston Electric Cooperative)
Wiregrass Electric Cooperative line crews are helping Lumbee River EMC restore power to its members. The crews are having to deal with flooding and other obstacles but they are more than prepared to help rebuild as quickly and safely as possible. (Photo courtesy: Wiregrass Electric Cooperative)
Flooding leads to alternative transportation for lineworkers at Sequachee Valley Electric Cooperative (Photo courtesy: Anothony Johnson)
Trimming and clearing downed trees is a big part of restoration efforts. (Photo courtesy: Randolph EMC)
A flooded Tri-County EMC substation in North Carolina. (Photo courtesy: Tri-County EMC)
This Brunswick EMC truck just may be the pot of gold at the end of the rainbow. (Photo courtesy: Brunswick EMC)
Flooding closes roads in Pee Dee Electric service territory (Photo courtesy: Pee Dee Electric)
Corn Belt Energy crews are assisting South River EMC near Fayetteville, North Carolina (Photo Courtesy: Corn Belt Energy)
Alabama's Cullman Electric Cooperative crew battle rain and wind to assist Brunswick EMC. (Photo courtesy: Chad Thompson)
Mutual aid and contract crews are using tracked equipment to reach damaged lines in the service territory of Lynches River EC near Pageland, South Carolina. (Photo by: Lynches River EC)
Driving through flooding, Corn Belt Energy crews are assisting South River EMC near Fayetteville, North Carolina (Photo Courtesy: Corn Belt Energy)
Crew from Randolph EMC working safely in hazardous conditions. (Photo courtesy: Randolph EMC)
Flooded road in Jones-Onslow EMC service territory near Jacksonville, North Carolina. (Photo courtesy: Jones-Onslow EMC)
Tree damage taking down lines in Jones-Onslow EMC service territory near Jacksonville, North Carolina. (Photo courtesy: Jones-Onslow EMC)
Corn Belt Energy crews are assisting South River EMC near Fayetteville, North Carolina (Photo Courtesy: Corn Belt Energy)
Corn Belt Energy crews are assisting South River EMC near Fayetteville, North Carolina (Photo Courtesy: Corn Belt Energy)
Tri-County dispatchers are on shifts and will continue to monitor the storm and outages. (Photo courtesy: Tri-County Electric Cooperative)
Brunswick EMC crews are methodically riding the lines to identify and safely remove trees from lines, like this one on Bricklanding Road. (Photo courtesy: Brunswick EMC)
Santee Cooper line crews hard at work to restore power. (Photo courtesy: Santee Cooper)
A series of leaning poles in Jones-Onslow EMC service territory near Jacksonville, North Carolina. (Photo courtesy: Jones-Onslow EMC)
Big trees cause big problems. Lucky for the members of Lynches River Electric Cooperative, they have awesome tree crews out in Chesterfield County, SC working to get these trees off the line and get power back on! (Photo courtesy: Lynches River Electric Cooperative)
Making repairs to the Davis Station substation. (Photo courtesy: Santee Electric Cooperative)
Middle Tennessee Electric Cooperative crews and equipment head out with Carteret-Craven Electric Cooperative crews to begin restoration in the aftermath of Hurricane Florence. (Photo courtesy: Carteret-Craven Electric Cooperative)
Power restoration in Roanoke EMC's service territory. (Photo courtesy: Roanoke EMC)
Apprentice lineman Zach Stewart gets ready to open a tap and change a 3-phase cross arm on the Four County system. (Photo courtesy: Sequachee Valley Electric Cooperative)
Crews from Four County EMC and assisting cooperative Sequatchee Valley wait for weather to allow restoration work to begin. (Photo courtesy: Four County EMC)
Downed trees disrupt more than power. (Photo courtesy: South River EMC)
York Electric Cooperative linemen are hard at work to replace and repair the broken poles to get members' power back on as soon as possible. (Photo courtesy: York Electric Cooperative)
High winds near the North Carolina coast are leading to downed trees, limbs and in this case a pole. (Photo courtesy: Carteret-Craven Electric Cooperative)
As the leading edge of rain comes in from Hurricane Florence, crews clear limbs and dead wood near roadside power lines. (Photo courtesy: Carteret-Craven Electric Cooperative)
Middle Tennessee EMC's 16 volunteers are part of more than 230 volunteers working with Carteret-Craven EMC to restore power in the wake of Hurricane Florence in North Carolina.
One lineworker carries a reminder of why safety is important. (Photo courtesy: Tideland EMC)
Lee Electric crews are replacing a broken pole and cross arm 2 miles east of Cypress Landing. (Photo courtesy: Tideland EMC)
Crews from Arkansas, Oklahoma and Texas have arrived to assist with potential outages at Blue Ridge EMC. (Photo courtesy: Blue Ridge EMC)
Safety of crews and employees is the top priority for Union Power Cooperative as they work to restore power. (Photo courtesy: Union Power Cooperative)
The last major obstacle before two circuits can be energized. (Greg Morris photo from Tideland EMC)
York Electric Cooperative crew working to get a tree off of the line causing the outage for our Lakeview Circuit 6 members near Coltharp Road and Hwy 21. (Photo courtesy: York Electric Cooperative)
Missouri lineworkers provide assistance to Santee Electric Cooperative in Florence County. Here they are wading through a swamp to pick up a line. (Photo courtesy: Santee Electric Cooperative)
Missouri lineworkers provide assistance to Santee Electric Cooperative in Florence County. (Photo courtesy: Santee Electric Cooperative)
Horry Electric Cooperative crew works on finishing up the replacement of two utility poles in the Socastee area that, once the lines are heated up, will restore service to about 1500 members. (Photo courtesy: Horry Electric Cooperative)
Pee Dee Electric Cooperative crews are faced with severe flooding, periods of heavy rainfall and wind gust that slow the restoration process. (Photo courtesy: Pee Dee Electric Cooperative)
Union Power Cooperative crews continue to make progress restoring power. (Photo courtesy: Union Power Cooperative)
Treacherous conditions and soft ground bring about downed lines. (Photo courtesy: Union Power Cooperative)
Union Power Cooperative lineworkers endeavor to work safely in dangerous conditions. (Photo courtesy: Union Power Cooperative)
Union Power Cooperative lineworker works in among the trees. (Photo courtesy: Union Power Cooperative)
Union Power Cooperative crews make progress restoring power, working in challenging conditions. (Photo courtesy: Union Power Cooperative)
Randolph EMC crews continue to report broken poles & downed spans of wire, which account for several prolonged outages. Most broken poles have resulted from trees outside the right of way falling onto power lines because of the heavily saturated ground. (Photo courtesy: Randolph EMC)
Nine Duck River EMC lineworkers and seven trucks are aiding crews from Lumbee River EMC where flooding is an ongoing issue. (Photo courtesy: Duck River EMC)
A downed pole in the road in Four County EMC service territory. (Photo courtesy: Four County EMC)
Flooding in Four County EMC service territory. (Photo courtesy: Four County EMC)
A broken pole dangles over the road in Four County EMC service territory. (Photo courtesy: Four County EMC)
Flooding in Four County EMC service territory. (Photo courtesy: Four County EMC)
Middle Tennessee Electric Membership Corporation works with crews from Carteret-Craven EMC to restore power. (Photo courtesy: Middle Tennessee EMC)
Monitoring outages and the storm at Pee Dee Electric (Photo courtesy: Pee Dee Electric)
Line crews at Pee Dee Electric face high winds and flooding (Photo courtesy: Pee Dee Electric)
Sequachee Valley Electric Cooperative crews continue to battle flood waters and the remnants of Hurricane Florence as they help Four County Electric Membership Corporation restore power in North Carolina. (Photo by Anthony Johnson)
Fallen trees in Four County Electric Membership Corporation service territory in North Carolina. (Photo by Anthony Johnson)
Sequachee Valley Electric Cooperative crews continue to battle flood waters and the remnants of Hurricane Florence as they help Four County Electric Membership Corporation restore power in North Carolina. (Photo by Anthony Johnson)
South River EMC doing whatever it takes to get the power back on. (Photo courtesy: South River EMC)
Tree down in Pee Dee Electric service territory. (Photo courtesy: Chickasaw Electric Cooperative)
Lineworkers from Tennessee's Chickasaw Electric Cooperative are seeing significant flooding as they assist Pee Dee Electric crews in restoring power. (Photo courtesy: Chickasaw Electric Cooperative)
The Perils of More Flooding
Co-ops are warning that more outages are possible particularly in areas that include newer commercial and residential developments served by buried power lines and ground-mounted transformers.
“Underground systems are not directly affected by toppled trees,” said Rob Ardis, an electrical engineer and CEO of Santee Electric Cooperative in Kingstree, South Carolina.
“The buried wires are heavily insulated for years of safe, dependable service, and the transformers sit above ground, covered from rain but in unsealed cabinets,” said Ardis, whose cooperative serves about 44,000 members in four counties. “We can’t seal the transformer cabinets, because the heat they generate needs a way to get out.”
Floodwaters can inundate the transformer cabinets, damaging internal components, and saltwater from storm surge can damage switch gears and other equipment, causing more outages.
Officials in South Carolina have warned that flooding could persist for several more days as waterways rise and fall as part of the natural drainage process. Some rivers in the Carolinas are rising more quickly than hydrologists forecast, and as many as 50 rivers in the Southeast and parts of the mid-Atlantic region could be pushed to or above flood stage in the days ahead.
Record rainfall in parts of the mid-Atlantic region this summer means trees there, still heavy with leaves, are at risk.
Co-ops Helping Co-ops
Mutual aid has been the muscle backing up the bone structure of the co-op network in areas hit by Florence. Co-op crews and their longtime contractors have logged thousands of miles to reach hard-hit areas and then taken guidance from co-op retirees, staking technicians, engineers and meter techs to make sure they are working where they can make the most impact getting service restored to as many members as possible.
“In the electric co-op world, teamwork means linemen and crews rally to support those without power,” said Kristie Aldridge, director of communications for North Carolina’s Electric Cooperatives. “Hundreds of crews, some from as far away as Alabama, Florida, Indiana and Minnesota, are assisting our North Carolina co-ops to form teams that will not stop until every light is on.”
Electric co-ops from more than a dozen states, including those from parts of North Carolina, South Carolina and Georgia that originally kept their crews available for local response, are now involved in power restoration where they are needed.
“Arkansas cooperatives have sent approximately 100 pieces of equipment that include service bucket trucks, bucket trucks, digger derricks, pickups and pole trailers,” said Rob Roedel, a spokesman for Arkansas Electric Cooperatives Inc., adding that more crews remain available should they be needed.
“Personnel from the Alabama Rural Electric Association are keeping in close touch with their counterparts in North Carolina so plans can be made to shift crews from one area to another, as the need arises,” said Lenore Vickrey, the association’s vice president of communications. She added that if they are needed, “the crews can expect to spend a week to 10 days helping restore power.”
About 175 co-op staffers from Georgia are also committed to the rebuilding effort, with equipment from 22 of the state’s co-ops now in the region.
“We have a network of cooperatives across the country that will spring into action and help a fellow co-op during emergencies and times of crisis,” said Harry Reeves, vice president of training, education and safety for Georgia Electric Membership Corp. “We have an unwritten agreement that says if we’re in trouble, they help us. In return, we help them.”
That mutual aid force is making a huge impact toward cutting outage numbers, and crews are being shifted around as work is completed.
“Thirty-three Missouri electric co-ops sent 182 cooperative lineworkers to the Carolinas to assist with storm cleanup,” said Jim McCarty, a spokesman for the Association of Missouri Electric Cooperatives. “Missouri sent both construction and service crews to help with the power restoration efforts.”
National Response to Power Outages
NRECA continues to work with the Department of Homeland Security, FEMA and top executives from the electric utility industry supporting a co-op response that could involve mutual assistance from across the nation for weeks to come.
“Major storms like Florence test our resolve, but also bring out the best in electric cooperatives as they work around the clock to reconnect local communities,” said NRECA CEO Jim Matheson.
“Daily phone calls with folks on the ground and those planning to travel to help restoration are coordinated by the statewide storm coordinators,” said Martha Duggan, NRECA’s regulatory issues director. “The information from those calls is helpful as we provide situational awareness to our federal partners.”
“This is a long-duration event, and we appreciate the ongoing leadership from DOE, DHS, and FEMA in helping to coordinate the industry’s response with federal, state, and local officials,” said Duane Highley, president and CEO of Arkansas Electric Cooperative Corp.
Highley co-chairs the Electric Subsector Coordinating Council, which works with federal partners and other stakeholders to help maintain and secure the nation’s power grid and other critical infrastructure.
ESCC officials have said the industry, its contractors, and state and federal agencies have committed about 40,000 people to the Florence response for the electric grid.
A bird's eye view of staged materials at Carteret-Craven Electric Cooperative. (Photo courtesy: Carteret-Craven Electric Cooperative)
Randolph EMC crews and contractors providing storm assistance gathered early this morning for a briefing & hot breakfast to fuel up to respond to any outages that might occur in the wake of Hurricane Florence. (Photo courtesy: Randolph EMC)
Support crew trucks at Carteret-Craven Electric Cooperative are loaded and ready to go. (Photo courtesy: Carteret-Craven Electric Cooperative)
Line crew from Hillsborough-based Piedmont Electric Membership Corporation head east to assist at Carteret-Craven Electric Cooperative (Photo courtesy: Piedmont EMC)
Pitt & Greene EMC staged with trucks, trucks and more trucks. (Photo courtesy: North Carolina's Electric Cooperatives)
Earl Jones, an apprentice line technician at Carteret-Craven EMC (left), coordinates restocking efforts as crews continue power restoration following Hurricane Florence. (Photo By: Lisa Galizia/Carteret-Craven EMC)
Six lineworkers from Virginia's Northern Neck Electric Cooperative headed to Carteret_Craven Electric Cooperative in North Carolina to assist with restoration. (Photo courtesy: Northern Neck Electric Cooperative)
Workers fuel up to face the storm at Pee Dee Electric (Photo courtesy: Pee Dee Electric)
Preparing to roll out before sunrise, (Photo courtesy: Carteret-Craven Electric Cooperative)
Crews prepare to head out for restoration work after pickup up poles and distribution system hardware from the Newport, North Carolina headquarters of Carteret-Craven Electric Cooperative. (Photo By: Lisa Galizia/Carteret Craven EC)
Myra Beasley, human resources director of Tideland EMC (center), runs a YMCA camp kitchen to help feed workers restoring power in the co-op’s service territory. (Photo By: Tideland EMC)
Cumberland Electric Membership Corporation sent 12 lineworkers along with three bucket trucks, two digger trucks and two pickup trucks to South River Electric Membership Corporation in Dunn, N.C. to assist with Hurricane Florence recovery efforts. (Photo Courtesy: Cumberland EMC)
Lineworkers from Tennessee's Chickasaw Electric Cooperative are assisting Pee Dee Electric crews in restoring power. (Photo courtesy: Chickasaw Electric Cooperative)
Southern Coals Kitchen in Fayetteville called in staff to prepare 400 lunch plates for South River EMC. (Photo courtesy: South River EMC)
Meriwether Lewis Electric Cooperative volunteers work on recovery with EnergyUnited in Statesville, NC. The crew says the rain is heavy but spirits are co-op strong. (Photo courtesy: Meriwether Lewis Electric Cooperative)
Surry-Yadkin EMC cooks are hard at work already this morning preparing breakfast for line crews before they head out. (Photo courtesy: Surry-Yadkin EMC)
Nine Duck River EMC lineworkers and seven trucks are aiding crews from Lumbee River EMC. (Photo courtesy: Duck River EMC)
Additional crews from Alabama, Virginia, and Tennessee arrive to assist Union Power Cooperative in restoration efforts. (Photo courtesy: Union Power Cooperative)
Eggs Up Grill in Conway delivers a grab-and-go lunch to Horry Electric crews, They had DEMCO from Mississippi and Beauregard crews from Louisiana with them, plus Davie Tree crews. (Photo courtesy: Horry Electric Cooperative)
Santee Electric Cooperative crews roll out before the sun rises. (Photo courtesy: Santee Electric Cooperative)
Crews reported for duty at 5:30 on September 16 at Tideland EMC's Pamlico County office. The co-op plans to have 120 people on the south side of the Pamlico River. (Photo courtesy: Tideland EMC)
Missouri linemen have arrived at Santee Electric Cooperative. They will be working in all four counties of Santee's service territory. (Photo courtesy: Santee Electric Cooperative)
Crews from Arkansas co-ops gather at Blue Ridge EMC's Pickens warehouse before going out in the field to restore power. (Photo courtesy: Blue Ridge EMC)
Materials handler Tim Ford and warehouse manager Pat Corbett cut wire as Hurricane Florence approaches at Carteret-Craven Electric Cooperative in Newport, North Carolina. (Photo courtesy: Carteret-Craven Electric Cooperative)
Florida's Clay Electric Cooperative sent 31 employees and the pictured "Marsh Master" to assist Brunswick Electric Membership Corporation. in North Carolina (Photo courtesy: Clay Electric Cooperative)
Pee Dee Electric Cooperative staff pack snacks for crew who will be in the field. (Photos courtesy: PEE DEE Electric Cooperative)
Caney Fork crews bound for Rockingham North Carolina to help restore power at Pee Dee EMC on September 14. (Photo courtesy: Caney Fork Electric Cooperative)
Asplundh tree crews stage themselves to provide assistance at North Carolina's Brunswick EMC. Note the Minnesota tags visible in this picture. (Photo courtesy: Brunswick EMC)
Contractor trucks staged at the Carteret-Craven Electric Cooperative headquarters. (Photo courtesy: Carteret-Craven Electric Cooperative)
Lineworkers from Jones-Onslow EMC in Jacksonville, North Carolina, met on Sept. 12 to discuss power restoration efforts in preparation for Hurricane Florence. (Photo courtesy: Jones-Onslow EMC)
Southwest Tennessee Electric Membership Corp. sent 10 lineworkers to Jones-Onslow Electric Membership Corp. in Jacksonville, North Carolina, to assist with Hurricane Florence recovery efforts. (Photo courtesy: Southwest Tennessee Electric Membership Corp.)
umberland Electric Membership Corporation sent 12 lineworkers along with three bucket trucks, two digger trucks and two pickup trucks to South River Electric Membership Corporation in Dunn, N.C. to assist with Hurricane Florence recovery efforts. (Photo courtesy: Cumberland EMC)
A Rutherford Electric Membership Corp. bucket truck on standby for the approaching storm. (Photo courtesy: Carteret-Craven Electric Cooperative)
Holston Electric Cooperative sent 9 lineworkers to Lumbee River Electric Membership Corporation in Red Springs, NC to assist with Hurricane Florence recovery efforts. Photo courtesy: Holston Electric Cooperative)
Seven trucks loaded with equipment and 10 men left Tennessee's Sequachee Valley Electric Cooperative headed to Four County Electric Membership Corp. in Burgaw, North Carolina, to assist with Hurricane Florence recovery efforts. (Photo courtesy: Sequachee Valley Electric Cooperative)
As the sun was coming up Sept. 12, seven trucks loaded with equipment and 10 men left Tennessee's Sequachee Valley Electric Cooperative headed to Four County Electric Membership Corp. in Burgaw, North Carolina, to assist with Hurricane Florence recovery efforts. (Photo courtesy: Sequachee Valley Electric Cooperative)
Storm restoration kits prepped and ready to go at Carteret-Craven Electric Cooperative. (Photo courtesy: Carteret-Craven Electric Cooperative)
Staffers from Rappahannock Electric Cooperative load crossarms and other equipment into trucks at a service center in preparation for Hurricane Florence restoration work. (Photo By: Rappahannock EC)